Bess

Tales of BESS #11 - Case study: Technical Due Diligence for BESS project: 17.75MW / 35.5MWh (FR) 

Oct. 2, 2025
2 minutes

Tales of BESS #11 – Case study: Technical Due Diligence for BESS project: 17.75MW / 35.5MWh (FR)

Technical Due Diligence for BESS project: 17.75MW / 35.5MWh (FR) 

Greensolver performed the technical due diligence for a standalone BESS asset underdevelopment in France 17.75MW/35.5MWh.

The scope of the work covered:

  • Regulatory:
    • Review of ICPE requirements and tracking of its development
    • Application of evolving regulatory requirements to technical specifications

 

  • Technical:
    • Review of CATL’s BESS Model: EnerOne+
    • Site Assessment and Review of the proposed layout
    • Design review and capacity to operate on primary reserve markets
    • Contracts review (Warranty, EPC, and O&M)
    • Augmentation Strategy Evaluation
    • Review of compliance with evolving regulatory requirements

Through the review of the regulatory requirements and their anticipated changes, the technical capabilities of the BESS project were optimized to ensure compliance and mitigate potential risks. Such work was ensured by advising the owner to:

  • Acquisition of rights to neighboring land to facilitate regulatory developments
  • Amend site layout to ensure safety
  • Consideration of additional sub-systems
  • Negotiation of improved terms for the warranty and O&M terms
Written by Nikko Talplacido
Blog

The Latest Renewable Energy News

What the Update to NFPA 855 Means for Energy Storage Safety ?

BESS-Picture-Databyte

Tales of BESS #14 – SPECIAL – Co-Located Asset : PV + BESS – Impact on Budget forecast​

BESS-Picture-Databyte

Tales of BESS #13 – SPECIAL – Support a developer in structuring its BESS projects: standalone and hybrid​

BESS-Picture-Databyte

Tales of BESS #12 – SPECIAL – Strategic and Financial Overview of French storage market​

Tales of BESS #10 – Case study: Technical Due Diligence on two Greek BESS projects: Totaling 100MW / 200MWh (GRC) 

Solar-Picture-databyte

Safety Concerns in Single-Axis Tracker PV Plants: Risks and Mitigation Strategies

BESS-Picture-Databyte

Tales of BESS #9 – Case study: Technical Due Diligence on two Greek BESS projects: Totaling 200MW / 400MWh (GRC)

BESS-Picture-Databyte

Tales of BESS #8 – Case Study: Invoicing Statements control: 20MW / 20MWh (UK)

Adjustment mechanism: Turning a regulatory obligation into an opportunity

Home Resources and insights Tales of BESS #11 – Case study: Technical Due Diligence for BESS project: 17.75MW / 35.5MWh (FR)